Integrated Projects Controls

• Estimating is based on solid experience in the heavy industrial mechanical field.
• Historical project data is maintained and utilized via MS Access Database.
• Estimates are formulated using detailed units of measure such as piece counts, footages, tons, etc.,
allowing for accurate quantitative analysis to then be performed.

• Comprehensive Project Tracking and Reporting of the estimate details provide regular accurate examination of project performance.
• NSE tracking reports include expended resources versus earned value comparisons, daily manpower expenditures and progress, and commodity curves.

• NSE’s accurate Project Details will provide a fully Resource Loaded Primavera Schedule to accurately forecast project completion.
• Schedule activities in the project tracking report allow each schedule activity to be progressed based on actual installed quantities. NSE updates progress without speculation and forecasts work accurately.